HP Performance Optimized Data Center (POD) 240a Quick Setup Guide
Site plan requirements and actions 23
•
Interface directly with the HP installation project manager to be sure clear lines of communication exist
during the installation and commissioning processes.
Site planning
A comprehensive site plan assists with the site design (MEP) and helps you to be sure that you use the best
possible HP POD 240e NA installation process. When creating a site plan, consider the following
information:
•
HP POD 240e NA site requirements detailed in this document ("
" on page
•
HP POD 240e NA site preparation drawing package ("
" on
•
HP POD 240e NA readiness checklist ("
" on page
•
HP POD 240e NA installation ("
" on page
The HP team can assist you by answering questions and by helping to guide you throughout the process.
Installation
HP POD 240e NA installation includes the following:
•
•
•
HP POD 240e NA lifting requirements ("
" on page
•
HP POD 240e NA storage requirements ("
" on page
•
Installation equipment staging
Staging for the following items must be identified and considered:
•
Truck and component staging
•
Installation equipment staging
•
Site traffic
•
Regulatory or local permits
Locations for the HP POD 240e NA and equipment
When preparing a site plan, identify where the HP POD 240e NA, and equipment used to assemble it, are
going to be placed. Discuss and plan the following items as applicable to the installation:
going to be placed. Discuss and plan the following items as applicable to the installation:
•
HP POD 240e NA location and order of assembly
•
Generator and UPS units
•
POD-related switchgear
•
Housekeeping pads for required electrical equipment
•
Crane capacity, location, and reach