HP Performance Optimized Data Center (POD) 240a Quick Setup Guide

Page of 39
 
Site plan requirements and actions  23 
 
Interface directly with the HP installation project manager to be sure clear lines of communication exist 
during the installation and commissioning processes. 
 
Site planning 
A comprehensive site plan assists with the site design (MEP) and helps you to be sure that you use the best 
possible HP POD 240e NA installation process. When creating a site plan, consider the following 
information: 
 
HP POD 240e NA site requirements detailed in this document ("
" on page 
) 
 
HP POD 240e NA site preparation drawing package ("
" o
page 
) 
 
HP POD 240e NA readiness checklist ("
" on page 
 
HP POD 240e NA installation ("
" on page 
) 
The HP team can assist you by answering questions and by helping to guide you throughout the process. 
 
Installation 
HP POD 240e NA installation includes the following: 
 
Installation equipment staging (on page 
) 
 
Locations for the HP POD 240e NA and equipment (on page 
) 
 
HP POD 240e NA lifting requirements ("
" on page 
) 
 
HP POD 240e NA storage requirements ("
" on page 
) 
 
Other structures (on page 
 
Installation equipment staging 
Staging for the following items must be identified and considered: 
 
Truck and component staging 
 
Installation equipment staging 
 
Site traffic 
 
Regulatory or local permits 
 
Locations for the HP POD 240e NA and equipment 
When preparing a site plan, identify where the HP POD 240e NA, and equipment used to assemble it, are 
going to be placed. Discuss and plan the following items as applicable to the installation: 
 
HP POD 240e NA location and order of assembly 
 
Generator and UPS units 
 
POD-related switchgear 
 
Housekeeping pads for required electrical equipment 
 
Crane capacity, location, and reach