Appendix B: Preparing for delivery 
Pre-delivery tasks 
Allow adequate time for planning, scheduling, obtaining permits, design approval, inspections, and so on. 
 
Installation prerequisites 
Before installing the HP POD 240e NA, verify that the following prerequisites are met: 
 
All components are delivered to the facility. 
 
The HP POD 240e NA and power distribution components are in the final location. 
 
Facility power, water, and drainage are at the final location. 
 
Provisions for properly grounding the HP POD 240e NA are made. 
 
Required clearances exist, including overhead. 
 
All trade personnel required for assembly are coordinated. 
 
HP POD 240e NA site readiness checklist 
Before installing the HP POD 240e NA, follow all steps listed in this guide, the site plan, and the following 
checklists. 
Architectural/environmental considerations 
 
Item  Description 
Sign-off 
Be sure that the following installation requirements are met and 
understood by the customer: 
 
POD load pads are in the proper location. 
 
Upon installation, the POD structure must be leveled to ≤ 
0.5º, which can be checked at that time with a surveyor’s 
transit. 
 
Shimming is only allowed at the load pads. 
 
Place shims in increments across the load pads to be sure 
that there is sufficient load transfer. 
 
Verify that the installation pad is capable of supporting the total 
POD solutions weight. 
 
Verify that the HP POD 240e NA site has provisions for 
grounding or a grounding system. 
 
Verify that the site pad is physically marked with the locations 
of all HP POD 240e NA load pads. 
 
Verify that the HP POD 240e NA is not in the direct path of any 
external heat loads, such as generators or a building AHU. 
 
Verify that the installation starting point has been identified and 
marked. This is the location where the first HP POD 240e NA 
section is placed during installation.