HP Performance Optimized Data Center (POD) 240a Quick Setup Guide
Appendix B: Preparing for delivery 30
Item Description
Sign-off
1
Verify that the HP POD 240e NA is not in a drainage path or
flood prone area to prevent water from entering the HP POD
240e NA. HP recommends setting the HP POD 240e NA on a
240e NA. HP recommends setting the HP POD 240e NA on a
raised site pad.
2
Verify that the water quality meets drinking water standards.
Adiabatic media water supply
Item
Description
Sign-off
1
Verify that the water pressure is between 20-70 psi (138-483
kPa) and that water temperature is between 1°C to 30°C
kPa) and that water temperature is between 1°C to 30°C
(34°F to 86°F).
2
Verify that the water instant flow-rate is no lower than the rated
flow of the fill solenoid valve (1.5 gpm maximum flow per
adiabatic unit, maximum instantaneous.)
3
Verify that water hardness is no greater than 40degFH or
equal to 400 ppm of CaCO3.
equal to 400 ppm of CaCO3.
4
Verify that demineralized water (preferred) or drinking
(potable) water is used.
(potable) water is used.
Power requirements
Item Description
Sign-off
1
Verify that the following requirements are complete:
•
Short circuit analysis
•
Arc flash study
•
Circuit breaker coordination studies
2
Verify that the power installation work is completed according
to the approved conduit routing drawings that show the exact
routes, plan view, sections, and elevations.
routes, plan view, sections, and elevations.
3
Verify that temporary site power for installation and
construction is planned and available.
construction is planned and available.
4
) per HP POD 240e
NA requirements.
General
Item Description
Sign-off
1
Verify the utility connection including the main utility
transformers and metering equipment.
2
Verify the third-party commissioning services that might be
required by the owner.
3
Verify that the HP Project Team activities are coordinated with
other site construction activities.