HP Performance Optimized Data Center (POD) 240a Quick Setup Guide

Page of 39
 
Appendix B: Preparing for delivery  30 
 
Item  Description 
Sign-off 
Verify that the HP POD 240e NA is not in a drainage path or 
flood prone area to prevent water from entering the HP POD 
240e NA. HP recommends setting the HP POD 240e NA on a 
raised site pad. 
 
Verify that the water quality meets drinking water standards.   
 
Adiabatic media water supply 
 
Item 
Description 
Sign-off 
Verify that the water pressure is between 20-70 psi (138-483 
kPa) and that water temperature is between 1°C to 30°C 
(34°F to 86°F).  
 
Verify that the water instant flow-rate is no lower than the rated 
flow of the fill solenoid valve (1.5 gpm maximum flow per 
adiabatic unit, maximum instantaneous.) 
 
Verify that water hardness is no greater than 40degFH or 
equal to 400 ppm of CaCO3. 
 
Verify that demineralized water (preferred) or drinking 
(potable) water is used. 
 
 
Power requirements 
 
Item  Description 
Sign-off 
Verify that the following requirements are complete: 
 
Short circuit analysis 
 
Arc flash study 
 
Circuit breaker coordination studies 
 
Verify that the power installation work is completed according 
to the approved conduit routing drawings that show the exact 
routes, plan view, sections, and elevations. 
 
Verify that temporary site power for installation and 
construction is planned and available. 
 
Verify adequate site power (on page 
) per HP POD 240e 
NA requirements. 
 
 
General 
 
Item  Description 
Sign-off 
Verify the utility connection including the main utility 
transformers and metering equipment. 
 
Verify the third-party commissioning services that might be 
required by the owner. 
 
Verify that the HP Project Team activities are coordinated with 
other site construction activities.