Page of 192
11. Let the generator run at full rated load for 20-30 minutes. 
Listen for unusual noises, vibration or other indications 
of abnormal operation. Check for oil leaks, evidence of 
overheating, etc.
12. When testing under load is complete, turn off electrical 
loads.
13. Set  the  generator  main  circuit  breaker  to  its  OFF  (or 
open) position.
14. Let the engine run at no-load for a few minutes.
15. Set the AUTO-OFF-MANUAL switch to OFF. The engine 
should shut down.
checkinG automatic operation
To  check  the  system  for  proper  automatic  operation, 
proceed as follows:
1.  Set generator main circuit breaker to its OFF (or open) 
position.
2.  Check that the AUTO-OFF-MANUAL switch is set to OFF.
3.  Turn  off the  utility  power  supply  to  the  transfer  switch, 
using means provided (such as a utility main line circuit 
breaker).
4.  Manually set the transfer switch to the UTILITY position, i.e., 
load terminals connected to the utility power source side.
5.  Turn  on  the  utility  power  supply  to  the  transfer  switch, 
using  the  means  provided  (such  as  a  utility  main  line 
circuit breaker).
6.  Set  the  AUTO-OFF-MANUAL  switch  to  AUTO. The 
system is now ready for automatic operation.
7.  Turn off the utility power supply to the transfer switch.
With  the  AUTO-OFF-MANUAL  switch  at  AUTO,  the 
engine should crank and start when the utility source 
power  is  turned  off.  After  starting,  the  transfer  switch 
should  connect  load  circuits  to  the  standby  side.  Let 
the  system  go  through  its  entire  automatic  sequence 
of operation.
With  the  generator  running  and  loads  powered  by 
generator AC output, turn ON the utility power supply 
to the transfer switch. The following should occur:
•  After  about  fifteen  seconds,  the  switch  should
transfer loads back to the utility power source.
•  About one minute after retransfer, the engine should
shut down.
SettinG the eXerciSe timer
This  generator  is  equipped  with  an  exercise  timer. 
Once  it  is  set,  the  generator  will  start  and  exercise 
every seven days, on the day of the week and at the 
time  of  day  specified.  During  this  exercise  period, 
the  unit  runs  for  approximately  12  minutes  and  then 
shuts down. Transfer of loads to the generator output 
does not occur during the exercise cycle unless utility 
power is lost.
PROCEDURE 8 kW UNITS:
A switch on the control panel (see Figure 3.1) permits 
selection of the day and time for the system to exercise. 
At the chosen time, perform the following sequence to 
select the desired day and time of day the system will 
exercise. Remember, seasonal time changes affect the 
exercise settings.
1.  Verify  that  the  AUTO-OFF-MANUAL  switch  is  set  to 
AUTO.
2.  Press  and  hold  the “Set  Exercise”  switch  for  several 
seconds. All the red LED’s will stop flashing immediately 
and the generator will start.
3.  The  generator  will  start  and  run  for  approximately  12 
minutes and then shut down. The exerciser is now set to 
run at this time of day each week. Example: If the “Set 
Exercise” is pressed on Saturday afternoon at 2:00 p.m. 
the  generator  will  start  and  exercise  for  approximately 
12 minutes every Saturday at 2:00 p.m.
10-20 kW - INSTALLATION ASSISTANT:
Upon first power up of the generator, the display inter-
face  will  enter  an  installation  assistant. The  assistant 
will  prompt  the  user  to  set  the  minimum  settings  to 
operate. These settings are simply: “Current Date/Time” 
and  “Exercise  Day/Time”. The  maintenance  intervals 
will be initialized when the exercise time is entered. 
The  exercise  settings  can  be  changed  at  any  time 
via the “EDIT” menu (see Appendix, “Menu System”). 
If  the  12  volt  battery  is  disconnected  or  the  fuse 
removed,  the  Installation  Assistant  will  operate  upon 
power  restoration. The  only  difference  being  that  the 
display  will  only  prompt  the  customer  for  the  current 
Time and Date. 
ALL UNITS:
note:  if  the  installer  tests  the  generator  prior  to 
installation,  press  the “enter”  key  to  avoid  set-
ting  the  exercise  time. this  will  ensure  that  the 
customer will still be prompted to enter an exercise 
time when the unit is first powered up.
note: the  exerciser  will  only  work  in  the  auto 
mode  and  will  not  work  unless  this  procedure 
is  performed. the  current  date/time  will  need  to 
be  reset  every  time  the  12  volt  battery  is  discon-
nected  and  then  reconnected,  and/or  when  the 
fuse is removed.
Part 5
Page 150
OPERATIONAL TESTS 
AND ADJUSTMENTS
sEctioN 5.1
sYstEm fuNctioNal tEsts