additional components.
5.3  External Staging Control Wiring
 WARNING
Improper field wiring may result in fire or explosion 
which can cause property damage, severe injury, 
or death. Make only wiring connections which are 
in accordance with the Installation and Operation 
manual.
 AVERTISSEMENT
Un câblage incorrect lors de l’installation peut 
causer un incendie ou une explosion pouvant 
entraîner des dommages matériels, de graves 
blessures ou la mort. Ne faire seulement que les 
connexions conformes au Manuel d’installation et 
d’exploitation.
The wiring methods in this section must be 
used to connect an external staging control, such as a 
multiple boiler control, building automation system, 
energy management system, etc.)  Other wiring 
methods may be unsafe.
Figure 15
 shows how to wire the external 
controller to the Copper Brute II’s field wiring panel, 
which is located on the right side of the Copper Brute 
II.
Most of the time, the number of stages from the 
external control will match the number of stages on 
the Copper Brute II.  However, in some instances, the 
controller will not have enough staging capability to 
work with all of the stages on a Copper Brute II unit 
(for instance, using an 8-stage external control with 
four 4-stage Copper Brute II units.)  In these instances, 
it is very important to follow the instructions in this 
section  
Figure 15
 shows how to combine stages on the 
Copper Brute II for those instances when the external 
controller cannot control all the stages available.
NOTE:  The only time Copper Brute II stages should 
be jumpered is when the Copper Brute II has an 
external control, and the Copper Brute II is used in 
Mode 6.  In all other modes, when the Copper Brute II 
controls its stages, the terminals shown in 
Figure 15
 
must NOT be jumpered.