GE
 
OPM_SGS_USM_10K_40K_0US_V010.doc 
51/88 Operating 
Manual 
SG Series 10, 20, 30 & 40 kVA 
7.2.3  Restore to normal operation after “total off” 
 
View of the panel after pressing the 
button “total off”
• 
All Contacts are open; 
• 
Rectifier,  Inverter and Static-Switch
shutdown. 
 
 
 
1. Reset  total off  by pressing and 
holding the “total off”  button and the 
inverter on ( I ) key simultaneously 
until the Rectifier starts. 
 
 
2.  Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case 
of External Battery.
 
 
 
3. Press inverter on ( I ) key. 
• 
Soft-start of Inverter indicated with 
blinking LED
• 
At the end of Soft-start the LED 
remains lit. 
• 
UPS output LED indicates Load on 
Inverter
 
The LCD must display on the main screen the status LOAD ON INVERTER.
 
 
 
End of procedure