Toshiba reliability in motion 1700 Manual De Usuario

Descargar
Página de 39
TOSHIBA 
 
18 
A.2 Once the option is set to the desired level, press and hold 
the Function Control button.  This will save the new load 
shed level setting.  The UPS will indicate that the value has 
been stored by blinking the LEDs.  After blinking the LED for 
a short time the UPS will exit the programming mode and 
return to bypass operation.  To return the system to normal 
operation switch the RUN/STOP switch back to the RUN 
position. 
 
B.  Output Enable/Disable After Input Overvoltage Backup.  Press 
the function control button.  The unit is now ready to change the 
output enable/disable after input overvoltage backup option.  
This is indicated by the 150% LED turning on.  This setting 
determines whether the UPS will go to bypass in the case of an 
input overvoltage fault. To change this setting press and hold the 
function control button. 
 
B.1 This setting is set to disable output at the factory.  Pressing 
the function control button causes the 100% LED to light, 
indicating output has been enabled.  Pressing it again will 
change it back to disabled and the 100% LED will go off.
 
B.2 Once the option is set as desired, press and hold the 
function control button to save the setting.  The UPS will 
indicate the setting has been saved by blinking the LED(s).  
The LED(s) will continue to blink for a short time after which 
the UPS will exit programming mode and return to bypass 
operation.  To return the system to normal operation switch 
the RUN/STOP switch back to the RUN position. 
 
C.  Reset Battery Installed Date.  This should be done whenever a 
new battery pack is installed.  Press the function control button. 
The unit is now ready to reset the battery installed date.  This is 
indicated by the Battery LED turning on.  Once this mode has 
been entered press and hold the function control button to reset 
the battery install date to the current date.  The UPS will indicate 
that the date has been reset by blinking the Battery LED for a 
short time after which the UPS will return to bypass operation.  
To return the system to normal operation switch the RUN/STOP 
switch back to the RUN position. 
 
Note:  It is not necessary that the unit’s internal clock be set to the 
correct date.  The UPS will track time relative to the battery installation 
date.  If it is desired to set the date, this can be done through remote 
communication.  For instructions on performing this operation refer to 
either the "UPSmart" or "Remote Eye II" manual depending on the type 
of remote communication being used.