Alliance Laundry Systems 70269701R4 Manual De Usuario

Descargar
Página de 66
Electrical Requirements
51
70269701
© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT
Ferrite Ring Installation
Gas and Steam OPL Micro Control Models Only
The ferrite ring provided in the literature packet must 
be installed over the power leads during connection of 
electrical service. The ferrite protects the sensitive 
electronic controls from destructive electrical 
disturbances which may be present on power lines to 
the machine. Failure to properly install the ferrite ring 
may result in damage to the electronic controls and 
will void control warranty.
To Install:
1. Immediately after connection of power leads and 
before applying power to machine, locate each of 
the incoming service leads including ground.
2. Snap the ferrite ring closed over all of the service 
leads inside of the control tray as shown. It is 
important that the ferrite ring be installed inside 
the control tray. Refer to Figure 14. Do not install 
the ferrite outside of the box or other area. Make 
sure that service leads are in the center of the 
ferrite before closing the ring so as not to pinch 
or damage leads.
Figure 14 
T383I
1
Ferrite Ring
2
Electrical Connections V.A.C.~
3
Ground Wire
1
2
3
}