Commissioning HTs 7–1
Hub installation
Chapter 7
Commissioning HTs
This chapter includes:
•
Prerequisites for commissioning – page 7–2
•
HT commissioning procedure – page 7–3
•
Checking component status – page 7–7
•
HT to RT connection tests – page 7–11
Commissioning refers to verification procedures to ensure that the
newly installed hub terminal (HT) is operational.
newly installed hub terminal (HT) is operational.
Note:
Most references in this chapter are to an HT. A hub may
consist of one HT but usually consists of multiple HTs. Each
HT—an ODU, IFL, and IDU—must be commissioned separately.
HT—an ODU, IFL, and IDU—must be commissioned separately.