Commissioning HTs   7–3
Hub installation
To commission the HT, you apply power and observe the CCM
LCD while the HT downloads software and configuration data
from the EMS. This verifies that the HT equipment is operational.
(However, the HT is not ready for service until SSIs have been
configured by the EMS operator.)
To observe software and configuration downloading, you power
up the IDU and observe the LCD on the CCM front panel. The
CCM displays the following sequences:
Startup diagnostics (SUDS)
Boot up
Software loading
Configuration loading
After configuration loading, the LCD shows this message:
HT       Freq 1A1
Disabled
(Frequency is specific to HT)
This display signals that downloading has completed, which
demonstrates that the equipment is operational. The HT is disabled
until SSIs are installed and configured (through the EMS). 
When SSIs are installed and configured, the operational status is
HT Enabled
.
7.2
HT commissioning
procedure
Summary