I n t r o d u c t i o n :    
1-2
The following table outlines the responsibilities for each installation group. The tasks are 
listed in the order they should be completed.
*Note: Replacement mats are ordered and maintained by Target. It is important for 
Checkpoint personnel to review the site survey and determine necessity of mats. If 
replacement mats are required, Checkpoint personnel must notify Target to have mats 
ordered and delivered in time for the upgrade to the existing pedestals. As a precautionary 
measure, Checkpoint technicians will carry a 15 by 10 foot mat to all installations.
Table 0.1
Installation/upgrade task list
Responsibility (Task)
Installation Group
*Acquiring replacement mat, if necessary
Target
Removing existing pedestals
Checkpoint
Repairing old drill holes, if necessary
Checkpoint Contractor
Removing existing floor mats
Checkpoint Contractor
Removing any bumper posts, if necessary
Checkpoint Contractor
Filling in old bumper post holes, if necessary
Checkpoint Contractor
Cutting new floor channel (trench)
Checkpoint Contractor
Installing walker duct
Checkpoint Contractor
Installing power supply boxes
Checkpoint Contractor
Running power from ceiling to floor
Checkpoint
Running power in walker duct to pedestals base
Checkpoint
Crimping power wires and installing connectors
Checkpoint
Running CAT 5 network cable and terminate at the power supply with 
appropriate length
Target
Running CAT 5 network cable from power supply to floor
Checkpoint Contractor
Running CAT 5 network cable in walker duct to pedestal base
Checkpoint
Installing connectors on the CAT 5 network cable
Target
Testing network connectivity
Target
Connecting CAT 5 cable to pedestal riser
Checkpoint
Connection power to pedestal riser
Checkpoint
Installing new pedestals
Checkpoint
Replacing floor mats, if necessary
Checkpoint Contractor
Testing new pedestals for EAS
Checkpoint
Testing new pedestals for UHF
Checkpoint