HP Performance Optimized Data Center (POD) 20cp Guía De Referencia

Descargar
Página de 37
 
Site requirements  15 
These actions must be performed for all associated parts of the electrical power train. The majority of the 
details and factors required to complete these studies are associated with the existing installed facility 
infrastructure. 
  
 
CAUTION: 
 Failure to complete these studies can cause serious issues with the electrical 
integration of the POD into your electrical system. 
  
 
Electrical power system configuration 
A preliminary meeting with the HP POD Electrical Engineering team is necessary to discuss your decision 
concerning capacity limitations and the impacts of this decision on the electrical design. 
A 1N electrical configuration can be achieved by providing all of the required electrical feeders from a 
common power source, common switchboards, and transformers. 
A 2N electrical configuration can be achieved by feeding parallel power paths from independent power 
sources, switchboards, and transformers.