Installation and commissioning
22
8
.03 
Commissioning the machine
 
● Check machine and in particular 
electric lines for damage before fi rst 
commissioning.
 
● Remove pin 1 of the oil reservoir 2 
(Fig. 8 - 08). 
The pin serves only to protect 
the machine from damage 
during transport and must not 
be used when sewing.
 
● Clean the machine thoroughly and oil it 
(see chapter 10 Care and maintenance).
 
● Have skilled personnel check if the ma-
chine can be operated with the available 
mains voltage.
Do not operate the machine if there is any discrepancy.
The machine may only be connected to an earthed socket!
Have home position of the machine drive verifi  ed by certifi  ed technicians 
before fi rst commissioning! Have settings carried out my technicians where 
required (see chapter 8.05)
8
.04 
Switching the machine on/off
 
● Switch the machine on (see Chapter 7.01, On/off switch).
Fig. 8 - 08
1