11.3  Testing Your Installation 
If you have followed the above instructions you will have wired your system to the following 
diagram: 
Ethernet 
 
1 Orange/White 
3 Green/White 
6 Green 
8 Brown 
4 Blue 
5 Blue/White 
7 Brown/White 
2 Orange 
Ethernet 
Ethernet 
LED/Reset 
signalling 
0V Floating
36V-55V 
Chassis 
1 Orange/White
3 Green/White
6 Green
8 Brown
4 Blue
5 Blue/White
7 Brown/White
2 Orange
Ethernet 
LED/Reset 
signalling 
0V Floating 
36V-55V 
PIDU Plus 
ODU
Surge Arrestor
ALPU-ORT 
Cable Screen 
Tower 
T-568B 
T-568B 
CON3
CON4
CON1
CON2
1
2
3
6
4
5
7
8
3
5
2
4
8
1
6
7
 
Figure 82 - Simplified Circuit Diagram (Only One Transtector Shown For Clarity) 
11.3.1 Pre-Power Testing 
Before plugging in the RJ45 to the PIDU Plus, check the following impedances at the RJ45: 
1.  Check the cable resistance between pins 7 and 4 at the RJ45. Check against column 2 in 
2.  Check the resistance between pins 8 and 5 at the RJ45. Check against column 3 in the 
3.  Check the resistance between pins 7 and 8 at the RJ45. The value should be greater 
than 1000 ohms.