Bradford-White Corp Water Heater BWCH Manual De Usuario

Descargar
Página de 64
Page 41
COPPER BRUTE II (500 - 2000)
 Caution
If the tank temperature control is set too high, a 
potential for hot water scalding may exist.
Mode 2:
  Primary secondary piping.
Install a “supply sensor” in the primary loop 
using the Bradford White part number R2014800 
sensor (included with every Copper Brute II unit). 
Connect the sensor to the “S C2” and “SUP S” 
terminals. 
You must provide an indication of the system’s 
heat demand by removing the jumper across the 
“ComD” and “HtD” terminals on the field wiring 
panel and connecting a zone valve or zone pump end 
switch, thermostat, aquastat or other contact closure to 
these terminals. If the “ComD” and “HtD” terminals 
are left jumpered, the control will always see a heat 
demand and remain in “Dem” mode, with the boiler 
pump running continuously. See 
Section 5.2
 for more 
information.
A secondary aquastat, such as for a separate heat 
exchanger for DHW, can be connected to the “Set D” 
and “Com D” terminals. A call for heat from these 
controls will start the boiler pump and cause the boiler 
to fire.
If the boiler is not a pump mounted model, a 
24VAC pump contactor may be connected to the 
“PMP” terminals to control a field installed pump.
Program the temperature control to use Mode 2. 
The 
AUTO/MAN
 switch must be in the 
AUTO
 position in 
this mode.
Mode 4:  Hydronic outdoor reset system 
without primary / secondary piping.
Bradford White strongly suggests the use of 
primary secondary piping with the Copper Brute II 
boiler. This piping style best ensures that the Copper 
Brute II will have proper water flow. However, non-
primary secondary methods can be used successfully, 
so this section has been included.
Install the outdoor reset sensor, Bradford White 
part number R2014000, and connect the leads to the 
“OD S” and “S C2” terminals.
You must provide an indication of the system’s 
heat demand by removing the jumper across the 
“ComD” and “HtD” terminals on the field wiring 
panel and connecting a zone valve or zone pump end 
switch, thermostat, aquastat or other contact closure to 
these terminals. If the “ComD” and “HtD” terminals 
are left jumpered, the control will always see a heat 
demand and remain in “Dem” mode, with the boiler 
pump running continuously. See 
Section 5.2
 for more 
information.
Reset Override: An additional thermostat or aquastat 
may be connected to the “Set D” and “Com D” 
terminals. A call for heat from either of these controls 
will start the boiler’s pump and cause the boiler to fire. 
If the boiler is not a pump mounted model, a 
24VAC pump contactor may be connected to the 
“PMP” terminals to control a field installed pump.
Program the temperature control to use Mode 4. 
The 
AUTO/MAN
 switch must be in the 
AUTO
 position in 
this mode.
Mode 5:
  Primary secondary piping with 
outdoor reset.
Install the outdoor reset sensor, 
Bradford White 
part number R2014000,
 and connect the leads to 
the “OD S” and “S C2” terminals. Install a “supply 
sensor” in the primary loop using the 
Bradford White 
part number R2014800 sensor
 (included with every 
Copper Brute II unit). Connect the sensor to the “S 
C2” and “SUP S” terminals. 
You must provide an indication of the system’s 
heat demand by removing the jumper across the 
“ComD” and “HtD” terminals on the field wiring 
panel and connecting a zone valve or zone pump end 
switch, thermostat, aquastat or other contact closure to 
these terminals. If the “ComD” and “HtD” terminals 
are left jumpered, the control will always see a heat 
demand and remain in “Dem” mode, with the boiler 
pump running continuously. See 
Section 5.2
 for more 
information.
A secondary aquastat, such as for a separate heat 
exchanger for DHW, can be connected to the “Set D” 
and “Com D” terminals. A call for heat from these 
controls will start the boiler pump and cause the boiler 
to fire.
If the boiler is not a pump mounted model, a 
24VAC pump contactor may be connected to the 
“PMP” terminals to control a field installed pump.
Program the temperature control to use Mode 5. 
The 
AUTO/MAN
 switch must be in the 
AUTO
 position in 
this mode.
Mode 6:  Boiler with external staging control 
(multiple boiler control, building 
automation system, energy 
management system, etc.)
Leave the jumper installed between “Ht D” and 
“Com D” terminals.  There are terminals on the field 
wiring panel that must be wired per the instructions in 
Section 5.3
 of this manual.  Other wiring methods 
may be unsafe.  The wiring in 
Section 5.3
 of this 
manual must be used.
The 
AUTO/MAN
 switch is located on the circuit 
board in the slide-out control panel on the front of the 
Copper Brute II.  This switch is placed in the manual 
position 
(MAN)
 when an external control is controlling 
the Copper Brute II stages.
Program the temperature control to use Mode 
6.  Mode 6 tells the Copper Brute II control that an 
external staging control is being used.