A.
  Install vent system in accordance with local building 
codes; or local authority having jurisdiction; or 
National Fuel Gas Code, ANSI Z223.1/NFPA 54, Part 
7, Venting of Equipment and/or CAN/CSA B149.1, 
Venting Systems and Air Supply for Appliances. Install 
any of the following for this Series 8HE Category I, 
draft hood equipped appliance:
1.  Type B or Type L gas vent. Install in accordance 
with listing and manufacturer’s instructions.
2.  Masonry or metal chimney. Build and install in 
accordance with local building codes; or local 
authority having jurisdiction; or Standard for 
Chimneys, Fireplaces, Vents, and Solid Fuel 
Burning Appliances, ANSI/NFPA 211 and/or 
National Building Code of Canada.
  Masonry chimney must be lined with approved 
clay flue lining or listed chimney lining system 
except as provided in ANSI Z223.1/NFPA 54, 
Paragraph 7.5.4(a): Exception:  Where permitted by 
the authority having jurisdiction, existing chimneys 
shall be permitted to have their use continued when 
an appliance is replaced by an appliance of similar 
type, input rating, and efficiency.
3.  Single wall metal vent. Allowed by ANSI Z223.1/
NFPA 54 under very restrictive conditions.
B.
  Inspect chimney and remove any obstructions or 
restrictions. Clean chimney if previously used for solid 
or liquid fuel-burning appliances or fireplaces.
Inspect existing chimney before installing boiler.  
Failure to clean or replace perforated pipe or tile 
lining will cause severe injury or death.
C.
  Install Draft Hood on canopy outlet. Maintain height 
from Jacket Top Panel to Draft Hood skirt as shown 
in Figure 1. DO NOT ALTER, CUT, OR MODIFY 
DRAFT HOOD.
Do not alter boiler draft hood or place any 
obstruction or non-approved damper in the 
breeching or vent system.  Flue gas spillage can 
occur.  Unsafe boiler operation will occur.
D.
  Install Blocked Vent Switch.  The Blocked Vent 
Switch Assembly consists of a strain relief bushing, 
power cord, and switch attached to mounting bracket.  
On Packaged boilers, the assembly is shipped attached 
to top of boiler. On Knocked Down boilers, the 
assembly is located in Combination Boiler Parts and 
Control Carton.
1.  Uncoil power cord.
2.  Position mounting bracket onto lower edge of Draft 
Hood skirt. Locate center tooth (with #10 sheet 
metal screw) on outside and other two teeth inside 
Draft Hood skirt. See Figure 23.
3.  Slide mounting bracket tight against lower edge of 
Draft Hood skirt. Position #10 sheet metal screw 
above skirt’s stiffening rib.
4.  Secure bracket in position by tightening #10 sheet 
metal screw against outer surface of Draft Hood 
skirt.
5.  Insert excess power cord through Jacket Right Side 
Panel hole. Remove slack.
6.  Position strain relief bushing around power cord. 
Pinch bushing’s two halves together and snap back 
into hole in Jacket Right Side Panel.
7.  Verify power cord, mounting bracket, and Blocked 
Vent Switch are secure and located as shown in 
Figure 23.
Do not operate boiler without Blocked Vent Switch 
Properly installed.
VI. Venting
Figure 23:  Blocked Vent Switch Installation