7 OPERATION 
 
 
7.1  PROCEDURES FOR SINGLE LP 33 Series 
 
 
7.1.1 Start-up 
of 
the 
LP 33 Series 
 
 
Before connecting hazardous voltages, make sure that:  
•  The connection to the electrical system has been performed by qualified personnel; 
•  The equipment frame has been correctly grounded to the main earth
•  Make sure that mains input protection is removed; 
•  All the panels removed to allow the UPS connection have been correctly reinstalled; 
•  The UPS switches Q1 and Q2 are OFF (Pos. 0); 
•  The battery fuses F5, F6, F7 (and eventual external fuses in case of external battery) 
are removed. 
 
This procedure must be performed for the first start-up following the installation, with the UPS 
completely switched Off and not powered. 
 
This procedure presupposes that the load is not yet supplied by the UPS system. 
 
 
NOTE ! 
The UPS can be started-up using the battery supply in case the input mains should be 
unavailable. 
To avoid an incidental battery
 discharge, it is recommended to proceed to the UPS 
start-up having the input mains
 available. 
 
 
 
1.  Switch ON the mains power at the input distribution panel
As a result the UPS performs a self-test and the LCD will show 
the following screen: 
 
EXECUTING MAINBOARD 
SELF TEST 
00000000000 
SELF TEST OK! 
 
 
 
NOTE ! 
In case the alarm “4410 - Mains bypass out of 
tolerance”
 persists, please contact your Service 
Center
 
 
 
2.  Insert the battery fuses F5, F6, F7 and eventual external fuses in case of external battery. 
 
 