Flat Ceiling Installation
1.  Cut a 11 
1
/
2
" square hole in ceiling using 
locating hole as a center point. Opening 
should be framed to 11 
1
/
2
" x 11 
1
/
2
" inside 
dimensions, as shown in Figure 8 on page 
9 using framing lumber the same size as 
ceiling joists. If area above ceiling is an 
insulated ceiling or an attic, nail firestop 
from top side. This prevents loose insula-
tion  from  falling  into  required  clearance 
space.  If  area  above  ceiling  is  a  living 
space, install firestop below framed hole. 
Firestop should be installed with no less 
than three nails per side (see Figure 15).
2.  Assemble  desired  lengths  of  pipe  and 
elbows necessary to reach from fireplace 
flue up through firestop. Be sure all pipe 
and  elbow  connections  are  fully  twist-
locked (see Figure 8, page 11).
3.  Cut a hole in the roof using locating hole 
as  a  center  point.  (Cover  any  exposed 
venting inStALLAtiOn
Continued
Figure 15 - Offset with Wall Strap and 45° 
Elbows
45° Elbow
Wall Strap
Roof Flashing
Ceiling Firestop
open  vent  pipes  before  cutting  hole  in 
roof.) The 11 
1
/
2
" x 11 
1
/
2
" hole must be 
measured on the horizontal; actual length 
may be larger depending on pitch of roof. 
There must be a 1" clearance from vent 
pipe  to  combustible  materials.  Frame 
opening as shown in Figure 9, page 11.
4.  Connect a section of pipe and extend up 
through hole.
 
Note:  If  an  offset  is  needed  to  avoid 
obstructions, you must support vent pipe 
every 3 feet. Use wall straps for this pur-
pose (see Figure 15). Whenever possible, 
use 45° elbows instead of 90° elbows. The 
45° elbow offers less restriction to the flow 
of flue gases.
5.  Place  flashing  over  pipe  section(s)  ex-
tending  through  roof.  Secure  base  of 
flashing to roof and framing with roofing 
nails. Be sure roofing material overlaps 
top edge of flashing as shown in Figure 
15. There must be a 1" clearance from 
vent pipe to combustible materials.
6.  Continue to add pipe sections until height 
of vent cap meets the minimum building 
code requirements described in Figure 7 
on page 8.
 
Note: You must increase vent height for 
steep roof pitches. Nearby trees, adjoining 
rooflines, steep pitched roofs and other 
similar  factors  may  cause  poor  draft  or 
down-drafting  in  high  winds.  Increasing 
vent height may solve this problem.
7.  Twist-lock  vent  cap  onto  last  section  of 
vent pipe.
2.  Set fireplace in desired location. Drop a 
plumb line down from ceiling to position 
of  fireplace  exit  flue.  Mark  center  point 
where vent will penetrate ceiling. Drill a 
small locating hole at this point.
3.  Drop a plumb line from inside of roof to 
locating hole in ceiling. Mark center point 
where vent will penetrate roof. Drill a small 
locating hole at this point.
Vent Termination Chart
Minimum Height
Roof pitch
Feet Min.
Flat to 6/12
1
6/12 to 7/12
1.25
Over 7/12 to 8/12
1.5
Over 8/12 to 9/12
2
Over 9/12 to 10/12
2.5
Over 10/12 to 11/12
3.25
Over 11/12 to 12/12
4
Over 12/12 to 14/12
5
Over 14/12 to 16/12
6
Over 16/12 to 18/12
7
Over 18/12 to 20/12
7.5
Over 20/12 to 21/12
8.0