Pre Start-Up Checklists
The following checklists are to help prepare the equipment before the Vilter Technician arrives at the 
jobsite.  Vilter recommends that a Trained Technician go through the following tasks.  The operating 
Manuals provided by Vilter, can be referenced for any type of questions or special instructions.  
Every Refrigeration unit includes a Vilter Start-Up (Confi rm on PO).  The following tasks are not included 
in the Vilter Start-up provided in your equipment purchase.  Any tasks below that are done by the Vilter 
Technician will take away from the pre-determined time that was provided with the equipment pur-
chase.  Vilter suggests that the Vilter Technician’s time be used during the start-up of the System and 
not for the below System Preparation.
Note: Each item below MUST be “Checked-Off”, Signed and Returned to the Vilter Service Department.  
Failure to do so will “Null & Void” future Warranty considerations.