Nortel Networks Option 11C Mini Manuel D’Utilisation

Page de 334
Page 92 of 332
 Chapter 6 — Installing the Option 11C Mini
553-3021-209
Standard 3.00
April 2000
Readiness checklist
Have you:
made sure that you received all the equipment that you ordered?
made sure your area meets all environmental requirements?
checked for all power requirements?
checked for correct grounding facilities?
developed an equipment layout plan for the system? See “Equipment 
layout plan” on page 69.
completed the card slot assignment plan? See “Card slot assignments” on 
page 77
.
assembled all the tools required to continue with the installation?
If you have completed all of the above items, you are ready to start the 
installation of the Option 11C Mini system.
Summary of installation procedures
The following list provides a summary of the Option 11C Mini installation 
procedures. Refer to the chapters and procedures indicated at the end of each 
step for important and detailed information related to installation.
1
2
Make sure that you have read and completed the instructions contained 
in the Planning section of this guide.
3
Make sure that system and site requirements have been met. See 
“Chapter 3 — System and site requirements” on page 45.
4
Make sure that you have created the equipment layout plan and card slot 
assignment plan. See “Chapter 4 — Creating an equipment layout plan 
and a card slot assignment plan” on page 69.