Initial Startup and Electrical Checks
18
6.0
I
NITIAL
 S
TARTUP
 
AND
 E
LECTRICAL
 C
HECKS
This section includes the procedures on how to install the paralleling system for the first time and 
how to perform initial system checks of each UPS individually before connecting them in parallel.
NOTICE
Miswiring power to the input terminal block (L1-L2-N-G) may damage the UPS.
For the initial installation, perform the following:
1. Verify that the input and output circuit breakers on UPS are Off (open). To find the circuit 
breakers, refer to the Liebert GXT2-10000RT208 user manual, SL-23444, available at the Liebert 
Web site, 
2. Verify that the parallel communication cables are disconnected from the parallel ports.
3. Verify that the UPS is completely Off.
4. Connect the UPS input power wires to the terminal block.
5. Connect the parallel POD utility main input. No load equipment should be connected at this time.
To start the initial electrical checks for each UPS:
1. Switch On (close) the UPS input and output breakers on the parallel POD of only the first UPS to 
be checked.
2. Measure the voltages of L1, L2, N, and G from the first UPS.
3. Switch On (close) the input and output circuit breakers, which are on the rear of the UPS.
4. Power on the UPS, and make sure it is operating normally. 
Refer to the Liebert GXT2-10000RT208 user manual, SL-23444, for UPS operation.
5. Make sure the UPS output voltage is correct. If the output voltage of the UPS must be changed 
with the configuration program, it must be done now.
Refer to the Liebert GXT2-10000RT208 user manual, SL-23444, for help on using the configura-
tion program.
6. Power Off the UPS, switch Off (open) the corresponding input and output breakers on the parallel 
POD and the Liebert GXT2-10000RT208 UPS.
7. Repeat the initial electrical checks on the second and third UPS to make sure each UPS in the 
paralleling system is operating normally and set for the same output voltage configuration.