6. Connect the system output cables between the output busbars (N3-U3-V3-W3 terminals) and the critical load and 
tighten the connections to 13 Nm (M8 bolt), to 26 Nm (M10 bolt), and to 50 Nm (M12 bolt). ENSURE CORRECT 
PHASE ROTATION
Warning 
If the load equipment will not be ready to accept power on the arrival of the commissioning engineer then ensure that the system 
output cables are safely isolated at their ends. 
 
UPS Battery Connections
 
 
7. Connect the battery cables between the UPS terminals (+/-) and its associated BCB. Connect screened auxiliary 
cables from each BCB control board to the auxiliary terminal block (X3). OBSERVE THE BATTERY CABLE 
POLARITY
.
 
Warning 
Do not close the BCB before the equipment has been commissioned. 
 
8. Refit the lower protective cover. 
 
Bypass
connections
W 2
Battery
connections
X 3
Rectifier
connections
V 1
U 1
W 1
N 1
U 2
V 2
Earth
N 2
Output
connections
V 3
N 3
U 3
W 3
Auxiliary
terminal block
*
*
*
Q 1
Q 2
Q 5
Q 3
 
Note: For split bypass operation,
ensure that the busbars (*)
between the bypass input and
rectifier input are removed.
 