Remington QFP40 Manuale Utente

Pagina di 68
Page 41
REMINGTON QFP40 Direct Vent FIREPLACE
250-4721   JUNE 2001
VERTICAL INSTALLATION INSTRUCTIONS (CONT.)
CATHEDRAL CEILING INSTALLATION
Step 1. Follow installation Steps 1 and 2 under vertical termination section.
Step 2. Using the plumb-bob, mark the centerline of the venting system on the ceiling,
and drill a small hole through the ceiling and roof at this point. From the roof,
locate the drill hole and mark the outline of the cathedral ceiling support box.
Step 3. Remove  shingles  or  other  roof  covering  as  necessary  to  cut  the  rectangular
hole for the support box. Cut the hole 1/8" (3mm) larger than the support box
outline.
Step 4. Lower the support box through the hole in the roof until the bottom of the box
protrudes at least 2" (51mm) below the ceiling (Figure 17). Align the support box
both vertically and horizontally with a level. Temporarily tack the support box in
place through the inside walls and into the roof sheathing.
Step 5. Using tin snips, cut the support box from the top corners down to the roofline,
and fold the resulting flaps over the roof sheathing (Figure 18). Before nailing it
to  the  roof,  run  a  bead  of  non-hardening  mastic  around  the  top  edges  of  the
support box to make a seal between it and the roof.  Clean out any combustible
material from inside the support box.
Step 6. Complete  the  cathedral  ceiling  installation  by  following  the  same  procedures
outlines in steps 4 through 8 for vertical terminations.
VENTING
FIG. 17
FIG. 18