 Performing acceptance tests
 Page 339 of 456
Communication Server 1000M and Meridian 1
Large System Installation and Commissioning
Figure 117
Blower unit removal
Testing the sysload
Use Procedure 61 to test the sysload (manual reload) function.
Procedure 61
Sysload test
1
Start the sysload:
Simultaneously press the MAN RST buttons (the bottom buttons) on 
both Call Processor Cards.
The following functions occur during a sysload:
The red LED at the top of the CPU column should light.
The major alarm indication should be displayed on all attendant 
consoles.