INSTALLATION PLANNING
There are two basic types of direct-vent in-
stallation:
•  Horizontal Termination
•  Vertical Termination 
Horizontal Termination Installation
IMPORTANT
Horizontal square terminations 
require only inner portion of wall firestop. Hori-
zontal installations using round termination require 
exterior portion of wall firestop (see Figure 14, 
page 12).
1.  Set the fireplace in its desired location and deter-
mine the route your horizontal venting will take. 
Do not secure the fireplace until all venting has 
been installed. Some installations require sliding 
the fireplace in and out of position to make final 
venting connections. Figures 14 through 18 on 
pages 12 through 14 show different configura-
tions for venting with horizontal termination that 
will help you decide which application best suits 
your installation. Check to see if wall studs or 
roof rafters are in the path of your desired vent-
ing route. If they are, you may want to adjust the 
location of the fireplace.
2.  Direct vent pipe sections and components are 
designed with special twist-lock connections.
Twist-Lock Procedure:
 The female ends of the 
pipes have locking lugs (indentations). These 
lugs will slide straight into matching slots on 
the male ends of adjacent pipes. Push pipe sec-
tions together and twist one section clockwise 
approximately one-quarter turn until the sections 
are fully locked (see Figure 8). Note: Horizontal 
runs of vent must be supported every three feet. 
Use wall straps for this purpose.
3.  Use a 45° elbow to connect venting system 
to fireplace flue collar. The elbow is designed 
to  be  twist-locked  onto  the  flue  collar  as 
described in step 2. IMPORTANT: Do not 
attempt to alter the configuration of the elbow 
by cutting, twisting, bending, etc.
4.  Assemble the desired combination of pipe and 
elbows to the fireplace flue collar. If there are 
long portions of venting run, pre-assembled 
pipe sections may be installed as subassem-
blies for convenience.
VENTING INSTALLATION 
INSTRUCTIONS
Continued
Figure 8 - Vent Pipe Connections
Female 
Locking Lugs
Male 
Slots
(Framing
Detail)
10 
3
/
4
"
(273 mm)
10 
3
/
4
" Inside Framing
(273 mm)
10 
3
/
4
"
(273 mm)
1
/
2
"
(216 mm)
Vent Opening
Combustible Wall
Vent Opening
Noncombustible Wall
Figure 9 - Vent Opening Requirements
Center of 
Hole
5.  Carefully determine the location where the vent 
pipe assembly will penetrate the outside wall. 
The center of the hole should line up with the 
center-line of the horizontal vent pipe. Mark the 
wall for a 10 
3
/
4
" x 10 
3
/
4
" square hole. Cut and 
frame the square hole in the exterior wall where 
the vent will be terminated. If the wall being 
penetrated is constructed of noncombustible 
material, such as masonry block or concrete, 
a 8 
1
/
2
" hole with zero clearance is acceptable 