Cisco Cisco Process Orchestrator 3.0 Guida All'Installazione
3-2
Cisco Process Orchestrator Installation Guide
OL-24931-02
Chapter 3 Configuring Cisco Process Orchestrator
Configuring Core Functions Adapter
Configuring Core Functions Adapter
The Core Functions Adapter provides the basic functionality in Process Orchestrator. Use the Core
Functions Adapter Properties dialog box to configure default task settings, automation summary report
location, and Return on Investment (ROI) calculations.
Functions Adapter Properties dialog box to configure default task settings, automation summary report
location, and Return on Investment (ROI) calculations.
This chapter provides instructions viewing and modifying the Core Functions Adapter properties.
•
•
Configuring Return on Investment Settings
When you create a process, you have the option to enter the equivalent time it would take to run the
process manually. This value is calculated against the hourly rate specified on this page to determine the
return on investment for the process.
process manually. This value is calculated against the hourly rate specified on this page to determine the
return on investment for the process.
To configure the ROI:
Step 1
Choose Administration > Adapters, right-click Core Functions Adapter and choose Properties.
Step 2
On the Core Functions Adapter Properties dialog box, click the ROI tab and specify the hourly rate (in
dollars) that it would cost to execute a process manually, then click OK.
dollars) that it would cost to execute a process manually, then click OK.
Configuring Task Expiration Settings
Use the Task Properties page to specify the default number of days used for the task expiration date. If
a task is opened on its expiration date, an internal event is raised which can be used to trigger a process.
Users will be able to modify the date manually on the appropriate task property page.
a task is opened on its expiration date, an internal event is raised which can be used to trigger a process.
Users will be able to modify the date manually on the appropriate task property page.
To define default task expiration:
Step 1
Choose Administration > Adapters, right-click Core Functions Adapter and choose Properties.
Step 2
On the Core Functions Adapter Properties dialog box, click the Task Properties tab.
Step 3
Under Task expiration days, modify the default task expiration date, then click OK.