Laser Link III Mainframe Electrical Connections,
 Continued 
Procedure 
Follow these steps to install power supply B. 
 
1. 
Physically secure the alternate (redundant) power supply in a suitable 
location near the mainframe. 
2. 
Connect the provided power interface cable to the redundant supply (female 
to male molex connection). 
3. 
Connect the four wires on the opposite end of the power interface cable to the 
terminal block of the power distribution board (J11) as follows: 
• 
+24 V DC to terminal 1 
• 
+24 V DC to terminal 2 
• 
Ground leads to terminals 3 and 4 
4. 
Ensure the Redundant Power/“B” Alarm switch is to the forward position on 
the EMIC module or the ON position on the Status Monitoring module. 
 
 
 
5. 
Continue to Chapter 3, Setup and Operation