Chapter 8 Installing Main Antenna Feeder System
ble, first wrap waterproof self-adhesive tape round the ground
cable close to a copper sheet, as shown in
.
F
IGURE
125 W
ATERPROOF
A
DHESIVE
T
APE
W
RAP
4. Clamp an outer conductor of feeder with a copper sheet of
ground cable and a snap spring and make the copper sheet
combined with the outer conductor.
5. Perform waterproof and sealed processing for junction between
ground kit and feeder. The methods are listed as follows:
i.
First wrap waterproof self-adhesive tape and then wrap PVC
adhesive tape.
ii. For waterproof self-adhesive tape, first wrap from lower to
upper layer by layer, then wrap from upper to lower layer
by layer, and finally wrap from lower to upper layer by layer.
During wrapping, the former layer covers a half of the next
layer.
6. The grounding terminal of ground kit can be connected to a
body of tower or a cable tray on the top of building. This cable
tray connects with the lightning net of building. Clear away
oil paint and oxide around the junction and cover a layer of
antioxidation cream on this area for good electricity contact.
Finally, cover a layer antirust paint again.
E
ND OF STEPS
.
Feeder Indoor Ingoing
Feeder Indoor Arrangement Principle
The arrangement principles of feeder into a room comply with the
following:
There are four big holes on a 12–hole feeder hermetic-window.
Every big hole has three small holes, every of which a feeder
passes through.
According to the serial No. on the engineering labels attached
on the feeder, lay out the feeder through three small holes in
the same big hole clockwise or anticlockwise.