2. Lead the -48V DC (blue) and -48V RTN (black) cables through
the cable inlet on the equipment top, as shown in
F
IGURE
28 DC P
OWER
C
ABLE
I
NLET
3. Lay out the power cable to the power distribution subrack along
the vertical cable tray on the left side of cabinet.
4. Screw off the screws on the protective cover at the left side of
power distribution subrack with a screwdriver, and take off the
protective cover.
5. Install respectively the –48V DC (blue) and –48V RTN (black)
cables to the connection terminals of the power distribution
subrack, the connection relationship as shown in
44