ZTE Corporation ZXMBW-RA25 Manuale Utente

Pagina di 99
 
ZXMBW RA25 Agile 2.5G Remote Radio Frequency Unit Installation Manual 
 
64      
Confidential and Proprietary Information of ZTE CORPORATION 
 
F
I G U R E  
4 7
 
G
R O U N D I N G  
C
A B L E  
W
R A P P I N G   W I T H  
W
A T E R P R O O F  
T
A P E
 
 
 
5.  Clamp the feeder external conductor with the grounding 
cable sheet copper and the circlip, so that the grounding clip 
sheet copper and the feeder external conductor are fully 
locked together.  
6.  Conduct the water prevention treatment to the joint of the 
grounding clip and the feeder by performing the following 
steps:  
i.  First wrap the waterproof adhesive tapes and then the 
PVC tapes.  
ii.  To wrap the waterproof adhesive tapes, wrap them layer 
by layer from bottom to top first, then from top to 
bottom once again, and finally from bottom to top, that is, 
three layers of them. During the process, make sure the 
upper layer overlaps the lower layer by about half the 
width of the tapes.  
7.  The grounding end of the grounding clip can be connected to 
the main tower body or the outdoor cable rack (connected to 
the lightning protection grid of the building) on the roof. 
Remove the paint and oxide within the radius of about 13 
mm at the connection place, and cover the clean area with 
antioxidant to ensure good electric contact. When the 
grounding end is connected, apply another coating of 
antirust paint.  
E
ND OF STEPS
 
Chassis Jumper Installation 
The chassis jumper must be installed between the main feeder 
and the chassis. Usually, the finished 2 m jumpers are used. You 
can also prepare the jumpers on site as per the actual length 
required.  
If the finished jumpers are used, they can be directly 
installed between the feeder and the chassis.  
If the jumpers are prepared on site, 1/2'' feeders  must be 
prepared through cutting according to the specific length of 
each jumper. Assemble the appropriate feeder connector