Overview  6 
Feature 
Specification 
Class 
Class1 
Ambient temperature 
2°C to 54°C (35.6°F to 129.2°F) 
Relative humidity 
0% to 100% humidity 
 
 
As part of the overall certification, relevant sections of the International Building Code have been 
applied as part of the design and evaluation. The current design supports wind loads up to 90 mph. 
 
Site assessment 
HP requires a detailed site assessment prior to planning and preparing the customer site location for the HP 
POD 20c. Consult with HP to schedule a site assessment. 
 
Site preparation 
Site preparation must be complete before the delivery of the POD for a timely installation and commissioning. 
The site must meet all pad, power, and chilled water requirements. 
 
Site safety and security 
Each customer site must have its own standard safety and security requirements. The HP Program Managers 
work with the customer to ensure adherence to the appropriate precautions. HP is not responsible for 
determining or enforcing safety or security requirements. The customer must conduct all health and safety 
evaluations of the HP POD 20c, only using HP as a support mechanism. 
 
Fire detection and suppression 
The fire suppression system, supplied as an optional component for the HP POD 20c, is a "Manufacturer 
Designed" system specifically designed for this HP product, in compliance with national standards. 
The HP standard suppression system includes a Novec 1230 clean agent system. However, if the customer 
or local AHJ requires specific modifications or a replacement, HP can assist in these actions at the expense 
of the customer. 
HP does not certify that the fire suppression system that is installed in the HP POD 20c meets all local and 
jurisdictional requirements. The customer is responsible for the following actions as related to the fire 
suppression system: 
 
Verifying that the POD suppression system meets local codes, including specific local requirements for 
initial and periodic inspections. 
 
Arranging for and receiving all required local permits, including initial commissioning as well as 
standard and repair maintenance. 
 
Arranging for the connection of the agent tanks, refilling of tanks, and all system testing, including 
pressure tests. All general maintenance of the suppression system must be completed by an authorized 
technician. 
Additional local requirements are not covered as part of the option price or basic installation and 
deployment services, unless specifically included in an executed Statement of Work.