Appendix B: Preparing for delivery  29 
Appendix B: Preparing for delivery 
Pre-delivery tasks 
Allow adequate time for planning, scheduling, obtaining permits, design approval, inspections, and so on. 
 
Installation prerequisites 
Before installing the HP POD 20c, verify that the following prerequisites are met: 
• 
All components are delivered to the facility. 
• 
The HP POD 20c and power distribution components are in the final location. 
• 
Facility power, water, and drainage are at the final location. 
• 
Provisions for properly grounding the HP POD 20c are made. 
• 
Required clearances exist, including overhead. 
• 
All trade personnel required for assembly are coordinated. 
 
HP POD 20c site readiness checklist 
Before installing the HP POD 20c, follow all steps listed in this guide, the site plan, and the following 
checklists. 
Architectural/environmental considerations 
   
Item 
Description 
Initial 
Verify that the site location supplies sufficient locations for support. Ensure that upon 
installation the POD can be leveled to less than or equal to 0.5º. If edge or point loading is 
used, ensure a center support can be accomplished using shims and so on, to ensure that the 
POD can be properly leveled. Shimming is around the perimeter in increments. Use a 
surveyor’s transit upon installation to check the POD leveling requirements. 
 
Verify that the pad can support the total weight of the HP POD 20c solution by verifying that 
load calculations have been performed by your engineering team. 
 
Verify that the site has provisions for grounding. 
 
Verify the HP POD 20c is not in the direct path of any external heat loads, such as generators.   
Determine the average local temperatures and ensure that adequate environmental 
protection is provided, such as cold weather protection, if required. 
 
Verify that the site altitude is less than 3,048 m (10,000 ft). 
 
When installing on an elevated surface, verify that the maximum height requirements for the 
circuit breaker actuator meet the national, regional, and local regulations. Verify that proper 
landings and the catwalk are planned for electrical cabinet access. 
 
Verify the planning for required egress routes for all HP POD 20c personnel doors, cargo 
doors, and service area doors, including landings, the catwalk, and stairs. 
 
Verify that the local Authorities are contacted, all applicable codes and site-specific location 
guidelines are reviewed, and all required permits are obtained.