Bunn VLPFCanada Manuale Proprietario

Pagina di 28
Page 24                                    
Location:
 
The Right switch is located in the front of the hood, 
above and to the right of the brew funnel.
Test Procedure:
1.  Disconnect the brewer from the power source and 
remove the wires from all three terminals of the 
Right switch.
2.  With  a  voltmeter,  check  the  voltage  across  the 
black and white wires. Connect the brewer to the 
power source. The indication must be 120 volts 
ac.
3.  Disconnect the brewer from the power source.
If voltage is present as described, proceed to #4.
If voltage is not present as described, refer to the  Wir-
ing Diagram and check the brewer wiring harness.
4.  Check for continuity across the two terminals on 
the left side of the switch when it is in the upper 
position. Continuity must not be present across 
these terminals in the lower position.
WHI  Tank Keep Warm Heater Lead
WHI to On/Left  Switch
WHI to Solenoid 
WHI Tank Keep Warm Heater   
         Lead
BLK to On/Left  Switch
BRN/BLK to Right  Decant-
er Warmer      
      
FIG. 19 RIGHT SWITCH TERMINALS
P1987
RIGHT SWITCH
SERVICE (cont.)
FIG. 18 RIGHT SWITCH
P2172.80
10179 060100
If  continuity  is  present  as  describe,  reconnect  the 
wires, the switch is operating properly. 
If continuity is not present as described, replace the 
switch.
Removal and Replacement:
1.  Remove all wires from the switch terminals.
2.  Compress  the  clips  inside  the  hood  and  gently 
push the switch through the opening.
3.  Push the new switch into the opening and spread 
the clips to hold the switch captive in the panel.
4.  Refer to FIG. 19 when reconnecting the wires.