HP Performance Optimized Data Center (POD) 40cp Manuale Utente

Pagina di 63
 
Installation 25 
5. 
Close the main breaker in the House panel on the exterior of the HP POD. 
 
6. 
Close the remaining breakers in the House panel one by one, following the panel schedule on the 
inside of the House panel. 
  
 
NOTE:
  If you are installing a high density HP POD, you must also close the main breaker in 
the electrical busway 3 panel. 
  
7. 
Close the main breakers in the electrical busway 1 and electrical busway 2 panels. 
 
8. 
Inside the HP POD, close the breaker on each drop box that is connected to a rack of IT 
components.  
9. 
Power up your remaining racks and IT components following your standard IT startup procedure. 
 
Commissioning the HP POD 
Commissioning your HP POD is an optional service and is customized based on your facility. A typical 
commissioning process includes the following tests: 
 
Tighten the electrical busway connections 
 
Verify accurate electrical installation 
 
Verify accurate mechanical installation 
 
Test the operation of the BMS and Cooling controls 
 
Test the operation of the smoke detection system 
 
Test the operation of EPO system