Preparing to Install the Lift 
 
Final Site Inspection 
Verify the surface the lift will mount to is smooth and level. This surface must be made from 3,500 psi 
reinforced concrete with a minimum thickness of 4”. 
Verify that there is enough space for the lifts foot print. Be sure to include space for the folding access  
ramp. (49” x 69”) 
 
Caution: Verify that the running clearance around the lift complies with 
any codes for your area. 
 
•  The horizontal gap between the edge of the platform and the upper landing must no less than 3/8” 
and no greater than 3/4”. 
•  The horizontal gap between the guard panel and any wall or barrier must be no less than 2” and 
no greater than 3”. 
•  It is recommended that a gate or door be installed at the upper landing. 
•  Verify that sufficient head room exists above the lift. The lift will require 6’ 8” of clearance above 
the platform floor when the lift is at the upper landing. 
 
Warning: The area between the floor where the lift is mounted and the top 
landing must be covered by a smooth vertical fascia. This is to to eliminate any pinch 
points between the platform and landing. 
 
Connecting to Electricity 
The lift will require a 115 VAC 20 amp grounded electrical outlet within 6 feet of the lift. 
Plug the lift directly into the power outlet. Do not plug anything else into same outlet as the lift. 
 
Warning: Do not ride on the lift until it has been anchored in place. 
 
Controller Harness Connections 
 
 
 
 
 
 
 
High Voltage 
Circuit Breaker 
(AC unit only) 
Platform 
Traveling Cable
Upper Landing 
Interlock
Upper & Lower 
Limit Switches
Low Voltage 
Circuit Breaker 
Safety Pan 
Jumper
Upper & Lower 
Call‐Sends