Since some leak test solutions, including soap and water, may cause corrosion 
or stress cracking, the piping must be rinsed with water after testing, unless it 
has been determined that the leak solution is non-corrosive.
Conversion of this unit from natural gas to propane or propane to natural gas 
CANNOT be done in the field.
Rinnai America
FF  Models
1)   A  manual  gas  control  valve  must  be  placed  upon  the  gas  supply  line  to  the  Rinnai  Water 
Heater. A  union  can  be  used  on  the  connection  above  the  shut  off  valve  for  the  future 
servicing  or  disconnection  of  the  unit.
2)   Check  the  type  of  gas  and  the  gas  inlet  pressure  before  connecting  the  Rinnai  Water 
Heater  if  the  Rinnai  Water  Heater  is  not  of  the  gas  type  that  the  building  is  supplied  with, 
DO  NOT  connect  the  water  heater.  Contact  the  dealer  for  the  proper  unit  to  match  the  gas 
type. 
3)   Minimum  and  Maximum  Gas  pressures  are  listed  below: 
 
*  Minimum  value  is  for  input  adjustment
  Natural  Gas: 
Minimum    6"  WC 
Propane  Gas: 
Minimum  10"WC 
    
Maximum  10.5"  WC 
 
Maximum  13.5"  WC 
 
4)   After  completion  of  gas  pipe  connections,  all  joints  including  the  heater  must  be  checked 
for  gas-tightness  by  means  of  leak  detector  solution,  soap  and  water,  or  an  equivalent 
nonflammable  solution,  as  applicable. 
5)   The  Rinnai  Water  Heater  must  be  leak  tested  before  it  is  placed  into  operation. 
6)   The  Rinnai  Water  Heater  and  its  individual  shut-off  valve  must  be  disconnected  from  the 
gas  supply  piping  system  when  pressure  testing  of  the  gas  supply  piping  system  at  test 
pressures  greater  than  1/2  psi  (3.5  kPa). 
7)   Always  use  approved  connectors  to  connect  the  unit  to  the  gas  line. Always  purge  the  gas 
line  of  any  debris  before  connection  to  the  water  heater. 
8)   The  Rinnai  Water  Heater  must  be  isolated  from  the  gas  supply  piping  system  by  closing  it's 
individual  manual  shutoff  valve  during  any  pressure  testing  of  the  gas  supply  piping  system 
at  test  pressures  equal  to  or  less  than  1/2  psi  (3.5  kPa). 
9)   The  Rinnai  Water  Heater  Installation  location  must  provide  adequate  Combustion  and 
Ventilation  airflow. 
I N S TA L L E R ’ S  I N S TA L L AT I O N  I N S T R U C T I O N S