Chapter 6. Maintaining Units
80
3ware Serial ATA RAID Controller User Guide for the Power Mac G5
To add a task schedule slot
1
Choose 
Management > Schedule
 from the menu bar.
The Scheduling page appears, showing the schedule for Rebuild/Migrate 
Tasks.
2
To view Verify Tasks or Self-test Tasks, select it from the drop-down list 
at the top of the page.
3
Scroll to the section of the Scheduling page that shows the task you want 
to add.
4
In the fields at the bottom of the section, select the Day, Time, and 
Duration for the task.
5
Click the 
Add New Slot 
button. 
The page refreshes and the new schedule is added to the list. 
                                      
Selecting Self-tests to be Performed
Two self-tests can be set: one to check whether UDMA Mode can be 
upgraded, and another to check whether SMART thresholds have been 
exceeded. (For more information about these self-tests, see the 3DM 
Reference section, “Scheduling page” on page 97.)
Initially, these tests are set to run every 24 hours. You can change the schedule 
for when they are run, and you can disable the tests, if you prefer not have to 
have them performed. 
                                      
To select self-tests to be performed
1
Choose 
Management > Schedule
 from the menu bar.
The Scheduling page appears, showing the schedule for Rebuild Tasks.
2
Select Self-test Tasks from the drop-down list at the top of the page.
Note:
 
The scheduled tasks can be added in any order. For example a new task 
scheduled for Tuesday (slot-2) will preempt the task originally scheduled for 
Wednesday (slot-1).
Note:
 
These tasks will only be run during scheduled times if they are checked in 
the Schedule Self-tests
 
section of the Scheduling page. If neither of the tasks is 
checked, self-tests will never run, even if you have scheduled time slots set.