Reliability Systems: A Maintenance Aid 
Page 6-22
Repair Procedures for High and Critical Reliability 
6
When all Standby SPE circuit packs have been upgraded, force the Active SPE 
to become the Standby SPE as follows:
1. Issue the 
status system
 command from the terminal. Look at the SPE and 
MODE fields in the upper left corner of the form to determine the status of 
the Standby SPE. Recall that the Standby SPE is labeled as either 
“standby,” “maint,” or “down.”
2. If the Standby SPE is labeled as “maint,” continue issuing the 
refresh 
spe-standby
 command followed by the 
status system
 command until the 
Standby SPE is labeled “standby.”
NOTE:
It may be necessary to issue the 
refresh spe-standby
 command 
multiple times to preempt all Standby SPE maintenance activity. If 
the 
refresh spe-standby
 command successfully completes five 
times without the Standby SPE becoming labeled “standby” on the 
status system form, wait 20 minutes. Issue the 
refresh spe-standby
 
command once more.
3. If the Standby SPE is labeled “standby,” issue the 
reset system 
interchange
 command from the G3MT. After the SPE-interchange is 
complete, log into the terminal, issue the 
status system
 command, and 
verify that the SPEs have reversed roles.
4. Then, follow the “Circuit Pack Replacement Procedure”
 for each circuit 
pack to be upgraded in the new Standby SPE.
Circuit Pack Replacement Procedure
This procedure 
does not
 apply to the TN768 Tone-Clock circuit pack. Please 
refer to “TONE-BD”, “TONE-PT”, or “TDM-CLK” in 
 for the procedure to replace the Tone-Clock circuit 
pack. 
NOTE:
See the flowchart of the procedure for installing or replacing Standby SPE 
Circuit Packs In Duplication Option Systems at the end of this section, for 
use as a circuit pack replacement maintenance aid.
The following procedure involves throwing the SPE Select Switches to 
hard-select the current Active SPE. After completing the circuit pack 
replacement procedure, verify that the SPE Select Switches have been returned 
to the AUTO position both by noting their position and by noting that the SPE 
Select Switch LEDs on the TN772 Duplication Interface circuit packs are not on.
1. Throw the SPE Select Switches, 
one at a time
, to force selection of the 
current Active SPE. If SPE B is currently the Active SPE, throw both SPE 
Select Switches, 
one at a time
, to the right. If SPE A is currently the Active 
SPE, throw both SPE Select Switches, 
one at a time
, to the left. Throwing 
the SPE Select Switches automatically disables shadowing.