5.4.4
Connection of the Loads
In  order  to  ensure  the  safety  of  personnel  during  installation 
work,  make  sure  that  the  connections  are  made  under  the 
following conditions:
No mains voltage present.
The loads are switched off.
UPS is switched off (display completely blank).
To disconnect the PROTECT 1., carry out the following steps:
Place the “maintenance switch” manual bypass on 
the back of the UPS in the “bypass” position. For 
this purpose, first remove the 4 screws of the 
cover (no. 3, p. 26/27). 
Put the mains input miniature circuit breaker (no. 2, p. 
26/27) to the “OFF” position.
Connect the loads as follows (terminals 1.3, p. 26/27): 
Connect  the  UPS  terminals         / PE  = ground,  N  =  neutral 
conductor, L = phase that are marked with “OUTPUT” with the 
corresponding terminals of your UPS subdistribution.
5.5
Connection of External Battery Modules
The  PROTECT  1.  requires  the  use  of  at  least  one  external 
battery  module.  Two  preconfigured  battery  cubicle  types  are 
available.  Both  versions  guarantee  an  increase  in  the 
attainable  standby  time  due  to  their  parallel  connection 
capability (see also chapter 2.3).
PROTECT 1.100
PROTECT 1.150
PROTECT 1.200
PROTECT 
1.100 BP
-
-
PROTECT 
1.BP20
The  two  cubicle  types  are  distinguished  in  the  following. 
Follow 5.4.1 if you use the PROTECT 1.100 BP or 5.4.2 when 
using the PROTECT 1.BP20.
No 
mix !