Replace an FPC or Quad-wide PIC
M40 Internet Router Hardware Guide
166
9.
Insert the appropriate cables into the cable connector ports on each PIC on the FPC. 
Secure the cables so that they are not supporting their own weight. Place excess cable 
out of the way in a neatly coiled loop, using the cable management system. Placing 
fasteners on a loop helps to maintain its shape.
10. Press and hold the FPC offline button on the craft interface. 
The green LED labeled 
OK
 blinks for about 5 seconds while the Routing Engine 
downloads the FPC software, the FPC runs its diagnostics, and the PICs housed in the 
FPC are enabled. Router forwarding operations then halt for about 200 ms while the 
Packet Forwarding Engine incorporates the memory on the new FPC into the memory 
buffers shared by all FPCs. When the FPC is online, the 
OK
 LED lights steadily and you 
can release the offline button.
You can also verify correct PIC and FPC functioning by issuing the 
show chassis fpc
 
11. If you are installing multiple FPCs, repeat Steps 2 through 10 for each one. Wait 
30 seconds after installing each FPC to allow the FPC and PICs to come online.
Figure 76:  Install an FPC
Do not let cable hang free from the connector. Do not 
allow fastened loops of cable to dangle from the ladder 
rack, because this stresses the cable at the fastening point.
Avoid bending fiber-optic cable beyond its minimum bend 
radius. An arc smaller than a few inches in diameter can 
damage the cable and cause problems that are difficult to 
diagnose.
1060
 LEDs and offline 
button
FPC
Extractor clip
Thumbscrew