9.
Place the concrete blocks on the mount so they are evenly
spaced, with the ends of each block anchoring both the
inner and outer base angles, as shown in figure 5-8.
Figure  5-8
Proper placement of concrete blocks on the mount
T0009060
10.
When the mount installation is complete, if the roof is
covered with gravel, replace gravel up to the outside edges
of the mount. See figure 5-8.
Do not replace gravel in the area inside the mount base.
Leave the rubber pad exposed.
This section explains how to install the standard nonpenetrating
roof mount on a corrugated metal roof.
Special requirements:
Pressure treated lumber, as specified in step 1 below,
and
Twelve 1–inch–long (2.5–centimeter) lag bolts.
1.
Obtain five pieces of pressure treated lumber, each 4 inches
by 4 inches by 8 feet long (10 centimeters by 10 centimeters
by 2.44 meters long).
2.
Important:
 Select an area of the roof that is supported by a
metal I–beam to install the mount.
3.
Cut the rubber pad into strips 4 inches wide by 8 feet long
(10 centimeters wide by 2.44 meters long).
4.
Use 5–penny shingle nails to nail one strip of rubber pad to
one surface of each piece of lumber. See figure 5-9.