MasterCard® PayPass™ Contactless Transit Pilots
Installation Guide
2
New York MTA Subway Upgrade
This procedure defines how to perform an upgrade to a phase 1 pilot installation to the phase
2 pilot installation. It does not define how to install the phase 2 installation into a subway
turnstile from scratch.
2 pilot installation. It does not define how to install the phase 2 installation into a subway
turnstile from scratch.
2.1
Background
Phase 1 of the pilot comprised the installation of a Secura and contactless card reader
in subway turnstiles on the New York subway. Communications between the Secura
and the payment platform was achieved using a modem dial-up.
in subway turnstiles on the New York subway. Communications between the Secura
and the payment platform was achieved using a modem dial-up.
For phase 2, the Secura and contactless card readers are being replaced. Note that the
existing mounting plates within the subway turnstile will be re-used and the following
installation process will outline how this shall be done. Communications shall now be
achieved using IP over an Ethernet cable.
existing mounting plates within the subway turnstile will be re-used and the following
installation process will outline how this shall be done. Communications shall now be
achieved using IP over an Ethernet cable.
2.2
What is Supplied?
The MTA Upgrade part number is: PPCR004.
It comprises:
1.
Contactless Reader Assembly
2.
Secura Control Unit Assembly
3.
Adapter Plate, 08840-01-R
4.
OTI Contactless Reader Cable, 08829-02-R
5.
LED Board Cable, 08828-02-R
6.
LAN Cable, 08836-01-R
7.
Solenoid Cable, 08827-01-R
2.3
Tools Required
The following tools are required to install the VeriFone-supplied equipment for the pilot
installations.
installations.
o
5mm Allen Key
o
4.0, 5.5, 7.0 and 8.0 AF Nut Spanners
o
T25 and T30 Torx Drivers
2.4
Installation Pre-requisites
The following pre-requisites must be in place before the installation can proceed.
1.
An ethernet cable has been run into the turnstile, terminated with a female RJ45
connection point.
connection point.
2.
A 3-Pin (110v) power socket has been run into the turnstile providing power within
these ratings: 100-240Vac 0.7A, 50/60Hz
these ratings: 100-240Vac 0.7A, 50/60Hz
3.
The phase 1 installation is still present in the turnstile.
4.
The Secura Control Unit is pre-loaded with the application software.