 10 
 
 
Gas Piping 
 
Note:  Install a sediment trap (drip leg) and a union 
connection ahead of the primary manual shutoff valve 
on the boiler.  Gas piping should be installed in accor-
dance with National Fuel Gas Code, ANSI Z223.1, 
latest edition, and any other local codes which may 
apply; in Canada see CAN/CGA-B 149. 
 
Note:
  See chart below for required pipe size, based on 
overall length of pipe from meter plus equivalent 
length of all fittings. Approximate sizing may be based 
on 1 cubic foot of natural gas per 1,000 Btu per hour 
input, i.e., 900,000 Btu per hour requires about 900 
cubic feet per hour.  (See Typical Boiler Operating 
Conditions, Section 4.3, for more information.) 
 
WARNING!  
All threaded connections must be made using a pipe 
compound that is resistant to the action of liquefied 
petroleum gases.  Do not use Teflon tape on gas line 
threads. 
 
 
 
 
 
 
Pipe Capacity for Natural Gas 
 
Equivalent Pipe Length
Maximum Capacity in Cubic Feet of Natural Gas per Hour 
Pressure Drop of 0.5 inch Water Column/Equivalent Length of 
Pipe (in feet) 
Nominal 
Iron 
Pipe 
Size 
(Inches) 
 
Internal 
Diameter 
(Inches) 
90º Ell 
(Feet) 
Tee 
(Feet) 
 
20 
 
40 
 
60 
 
80 
 
100 
 
150 
 
200 
1-1/4 
1.380 
3.45 6.9 
950 
      
1-1/2 
1.610 
4.02 8.04 
1,460 
990 
810 
    
2.067 
5.17 
10.3 
2,750 1,900 1,520 1,300 1,150  950  800 
2-1/2  2.469 
6.16 
12.3 
4,350 3,000 2,400 2,050 1,850 1,500 1,280 
3.068 
7.67 
15.3 
7,700 5,300 4,300 3,700 3,250 2,650 2,280 
4.026 
10.1 
20.2  15,800 
10,900 8,800 7,500 6,700 5,500 4,600 
 
 