Utica Boilers UB90-100 インストール手順
10
Natural Gas
LP
MBH
CO
2
CO
MBH
CO
2
CO
50
8.7- 9.7
< 100
50
10.0 - 11.1
< 100
75
8.7- 9.7
< 100
75
10.0 - 11.1
< 100
100
8.7- 9.7
< 100
100
10.0 - 11.1
< 100
Table 1 - Manufacturer Settings
14. Install top boiler panel.
15. Turn on electric and gas to boiler
16. Resume operation using OPERATING
INSTRUCTIONS found on Operating Instructions
label on boiler or in Installation, Operation &
Maintenance Manual.
17. Verify proper operation by following START
UP PROCEDURE in Installation, Operation &
Maintenance Manual.
18. Verify Combustion:
A. Adjust gas pressure for optimal A/F ratio.
Gas pressure and fl ow will be lower after kit
installation. Refer to table 1 for combustion
settings.
B. Install adjustment screw and cover. Verify
settings.
C. Operate boiler thru several cycles after setting
the gas pressure to verify ignition quality.
19. Attach upgrade label next to rating plate. See
fi gure 23.
20. Install front jacket panel(s).
Figure 23 - Label Placement
HSI Installation