3.0  INSTALLATION  
 
3.1
  
R
ECEIVING AND 
S
TORAGE
 
 
3.1.1  Initial Inspection 
Upon receiving the boiler, inspect it for signs of 
shipping damage.  Since some damage may be hidden, 
we recommend unpacking the boiler and removing the 
top cover and inspecting the boiler.   
Verify that the total number of pieces shown on the 
packing slip agrees with those actually received. 
 
Important:  note any damage, suspected potential 
damage, or shortage of materials on the freight bill 
and immediately notify the carrier.  File all claims 
for shortage or damage with the carrier.  Claims 
for hidden damages must be filed with your carrier 
within 7 days.  The boiler carton is equipped with a 
“Tip (N) Tell”.  If  "Tip (N) Tell” arrow point is 
blue, that indicates that the package has been on its 
side or tipped over in transit.   
 
3.1.2  Storage Prior to Installation 
If the boiler is not installed immediately, it must be 
stored in a location adequately protected from the 
weather, preferably indoors.  If this is not possible, 
then it should remain in the shipping container and be 
covered by a tarpaulin or other waterproof covering. 
Note: controls and other equipment that are 
damaged or fail due to weather exposure are not 
covered by warranty.
 
 
 
3.2
  
C
OMPLIANCE WITH 
C
ODES
 
The P-K MACH Series
 
Boiler with standard 
components and with many options complies with 
American National Standard/CSA Standard ANSI 
Z21.13/CSA 4.9, latest edition, Gas-Fired Low 
Pressure Steam and Hot Water Boilers.   
The heat exchanger is constructed and stamped in 
accordance with ASME Boiler and Pressure Vessel 
Code, Section IV for 50 psig maximum operating 
pressure and/or 200º F maximum temperature.   
Other codes or approvals which apply will be labeled 
on the boiler. 
Installation of the boiler must conform to all the 
requirements of all national, state and local codes 
established by the authorities having jurisdiction or, 
in the absence of such requirements, in the U.S. to the 
National Fuel Gas Code, ANSI Z223.1/NFPA 54, 
latest edition.  In Canada, the equipment shall be 
installed in accordance with the current Installation 
Code for Gas Burning Appliances and Equipment, 
CAN/CGA-B.149, and applicable Provincial 
Regulations for the class, which should be carefully 
followed in all cases.  Authorities having jurisdiction 
should be consulted before installations are made. 
Where required by local codes, the installation must 
conform to American Society of Mechanical 
Engineers Safety Code for Controls and Safety 
Devices for Automatically Fired Boilers (ASME 
CSD-1). 
In the Commonwealth of Massachusetts (a) this unit 
must be installed by a licensed pipe fitter / plumber, 
(b) field installed gas cocks must be “T” handle type, 
and (c) piping of condensate shall conform with the 
State Plumbing Code. 
 
 
3.3
  
S
ETUP
 
 
3.3.1  Foundation 
Provide a firm, level foundation, preferably of 
concrete. 
 
Note:  The boiler may be installed on a combustible 
floor; however, the boiler must never be installed on 
carpeting. 
 
3.3.2  Placement 
The boiler must be level to function properly.  To 
assist in leveling the boiler, the four (4) adjustable leg 
bolts (1/2"- 13 NC) must be installed.  The adjustable 
legs are also necessary to provide adequate floor