3002503   11.06
Sidewall 
Venting
Vertical 
Venting
  
The figure below shows typical installation arrangements:
  
3.3 Mounting of Power Venter
 
The power venter can be installed in a variety of positions. It can be    
suspended from a ceiling or placed on a shelf/floor. Placement on a  
 
shelf requires special hardware and vibration dampers.
 
Suspension from a ceiling does not require any special hardware    
 
other than threaded rods, nuts, and hangers.  
 
Follow Fig. 4 and 5. when suspending the power venter from a  
 
 
ceiling.  Fig. 4 shows which mounting legs to use when installing  
 
 
the power  venter in its normal position with inlet in the back and  
 
 
 outlet on the top (installation between horizontal and vertical  
 
 
chimney). Fig. 5 shows which mounting legs to use when installing    
 
 the power venter with inlet on the bottom and outlet on the side  
 
 
(installation for sidewall venting). 
 
1. Once the position has been determined, hang four threaded  
 
 
  rods from hangers above, and slide the rods through the mounting  
 
  holes in the mounting legs. 
 
2.  Level the power venter.
 
3.  Secure the legs with washers and nuts.
 
 
Warning! Never install the power venter so the motor 
points down. This will shorten the life. The min. 
clearance to combustibles is 24 inches.
Threaded rod
Nuts
Mounting legs
UP
Threaded 
rods
Mounting 
legs
UP
Nuts
Fig. 3