Site Preparation
Site Preparation Checklist for EX3200 and EX4200 Switches
The checklist in Table 24 on page 81 summarizes the tasks you need to perform
when preparing a site for EX3200 or EX4200 switch installation.
Table 24: Site Preparation Checklist
Date
Performed By
For More Information
Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed
switch tolerances.
Power
Measure distance between external power
sources and switch installation site.
Locate sites for connection of system
grounding.
Calculate the power consumption and
requirements.
Hardware Configuration
Choose the number and types of switches you
want to install.
Rack or Cabinet
Site Preparation Checklist for EX3200 and EX4200 Switches
81