Stacking Recommendations
The purpose of this section is to collect notes on recommended procedures and expected behavior 
of stacked managed switches. Procedures addressed initially are listed below. 
Initial installation and power-up of a stack. 
Removing a unit from the stack
Adding a unit to an operating stack
Replacing a stack member with a new unit
Renumbering stack members
Moving the master to a different unit in the stack
Removing a master unit from an operating stack
Merging two operational stacks
Preconfiguration
Upgrading firmware
Migration of configuration with a firmware upgrade
General Practices
When issuing a command (such as move management, or renumber), it is recommended that 
the command has fully completed before issuing the next command. For example, if a reset is 
issued to a stack member, use the show port command to verify that the unit has re-merged 
with the stack, and all ports are joined before issuing the next command.
When physically removing or relocating a unit, always power down the unit before 
disconnecting stack cables.
When reconnecting stack cables, connect them before powering up the unit, if possible, and 
insure a good connection by tightening all connector screws (where applicable).