Step Action 
1.   
Plug the DataNET Hub Signal Equalizer Board into the se-
lected Port interface connector. 
2.   
Connect the board’s pig tail leads to the corresponding hub 
downlink port channel; red lead to (+) terminal, black lead to 
(-) terminal and white lead to Gnd terminal. See Figure 2-1. 
Master Port
Connectors
TB15 – TB18
 
3.   
Connect the downlink signal wires to the removable port 
connector (TB1) on top of the equalizer board. Positive to 
(+) terminal; and Negative to (-) terminal. See Figure 2-1. 
.
SW2
SW1
SW3
TB1Port
Connector
Board
Connector
GND
-
+
 
4.   
If conduit is used the cable shield is only terminated at one 
end of the cable. If shield is terminated at this end connect it 
to terminal 3 (GND) on board. If using cable gland connec-
tors, cable gland will always connect the shield to the chas-
sis. 
5.   
Set the switches on the board to the correct settings; see 
DataNET Hub Signal Equalizer Board Settings page 34. 
 
Down Link Wiring with  
DataNET Hub Signal 
Equalizer Board