Vermont Casting DVT38IN 사용자 설명서

다운로드
페이지 48
18
Chateau™
20011956
Horizontal Termination
The vent must rise vertically a minimum of 24” (610mm) 
off the top of the unit, before the first elbow. The hori-
zontal run may extend up to 20’ (6 m) and include a ver-
tical rise of up to 40’ (12 m). (Fig. 16) Horizontal termi-
nation must also meet the criteria shown in Figures 13 
& 14.
• 
Approved vent systems must terminate above and 
including the heavy line in Figure 16.
• 
Two 45° elbows may be substituted for each single 
90° elbow.
• 
With a rise between 2’ - 4’, one (1) 90° or two (2) 45° 
elbows may be used.
UP
FP1368
DVT44
5/03
Pipe Section
Pipe 
Rim
Pipe 
Rim
Hem
Lance
FP1368
Fig. 15  Install pipe, listening for the snap-lock to fasten.
Vertical Termination
A vertical vent system must terminate no less than 12’ 
(3.66 m) and no more than 40’ (12 m) above the appli-
ance flue collar. A 2’ (610 mm) vertical section must be 
installed before any offset. A maximum of 20’ (6.1 m) 
horizontal and three (3) 90° elbows may be installed 
with a minimum of 12’ (3.66 m) vertical section above 
the flue collar of the unit. Refer to Page 22, Figure 27 
for more information. 
A vertically terminated vent system must also conform 
to the following criteria:
• 
No more than three (3) 90° elbows may be used.
• 
Two (2) 45° elbows may be substituted for one (1) 
90° elbow. No more than six (6) elbows may be 
used.
• 
Vent must rise a minimum of 2’ (610 mm) before 
offset is used. 
• 
Termination height must conform to roof clearance 
as specified in Figure 34.
General Information 
Assembling Vent Pipes
SK8 Venting Pipes 
Canadian Installations:
The venting system must be installed in accordance 
with the current CSA-B149 .1 installation code.
USA Installations:
The venting system must conform with local codes and/
or the current National Fuel Gas code  ANSI Z223.1/
NFPA 54.
Only venting components manufactured by CFM Cor-
poration can be used in Direct Vent systems. 
NOTE: The joints of the inner pipe (flue pipe) must be 
taped with 550°F or higher temperature metal adhesive 
tape that meets the requirements of F.A.R. 25.853(a) 
High temperature sealant milpack or stove cement of 
550°F or higher could be used instead. The joints of 
the outer pipe (fresh air pipe) must be taped with 315°F 
or higher temperature metal adhesive tape or the use 
of high temperature milpack or stove cement would 
be applicable. When using the unitized 30°, 45° or 90° 
elbows, apply 1/4” bead of high temperature, 550°F or 
higher, sealant (milpack or stove cement) to the joint of 
the inner pipe (flue pipe) and the straight section as it is 
impossible to be taped. The outer pipe must be taped 
with 315°F high temperature metal adhesive tape for 
proper sealing.
Start by attaching the first vent pipe section to the collar 
on top of the fireplace. In order to attach the first pipe 
section, it may be necessary to remove the top shield. 
Remove four (4) screws securing top shield, install first 
pipe section and replace top shield.
Install the pipe as shown in Figure 15. When you get a 
good lock, you will hear the pipe clearly snap together. 
Once sections are snap-locked in place, it is extremely 
difficult to get them apart. Make sure the pipe is firmly 
snapped and locked together as each pipe section is 
mounted. When using 45° or 90° elbows, it is accept-
able to use three (3) screws (not supplied) at the joint 
between the vertical SK8 pipe and the elbow to ensure 
no separation.
When installing elbows, follow the same procedure.  
The joints of inner and outer elbow must be taped with 
UL approved high temperature metal adhesive tape for 
proper sealing. Be sure to always attach straps on up-
per elbow to a structural framing member.
For vertical installations, continue installing the pipe as 
required until pipe is installed up through the ceiling. At 
this point, you must install a firestop spacer.